Contract Type | Construction |
Location | Zabol, Iran |
Executive stage | Final Hanover |
Physical Progress | 100% |
Commencement Date | Jan., 27, 2006 |
Initial Duration | 18 months |
General works’ Quantity | |
Earth works | 90,000 m³ |
concreting | 32,000 m³ |
Reinforcement | 4,000 tons |
Form working | 74,000 m² |
Metal works | 3,000 tons |
Brief Description & Technical Specification
Zabol cement factory is the only one in the region. The main aim of the factory establishment is to support the region employment, reduce the cement price by reducing or omitting shipment distance fee and to improve the export capability.
BolandPayeh scope of work in this contract is to construct all parts of the cement factory including the returning clinker silos, the clinker silos, the clinker transfer system, the cement transfer system, the cement silos, etc. The plant's production capacity is 3,300 tons per day.