Contract Type | Construction |
Location | Bandar’ Abbas, Iran |
Executive stage | Under Construction |
Physical Progress | 100% |
Commencement Date | Sep., 12, 2015 |
Initial Duration | 24 months |
General works’ Quantity | |
Earth works | 400,000 m³ |
concreting | 32,000 m³ |
Reinforcement | 5,000 tons |
Form working | 50,000 m² |
Brief Description & Technical Specification
Tose’e Ab Asia desalination plant is the largest one in Iran. The project consists of desalination units with a total capacity of one million cubic meters per day from seawater using Reverse Osmosis method (SWRO) technology.
The desalinated water will be used for potable and industrial applications based on three 8-hours shifts and 345 working days in an area of about 155 hectares in western Bandar’ Abbas city. The main water consumers of the project are Gole-Gohar industrial complex, Chadormalou industrial complex, and Sarcheshmeh copper Factory.
BolandPayeh service in this project is excavation, backfilling, pilling, reinforcement, form working, concreting, waterproofing and metal works of the intake structure and storage yard of the complex.