Stabilization of Tajan Rive

status:

is finished

contract type:

c

project domain:

water

location:

Iran , Mazandaran

Stabilization of Tajan Rive
Contract Type Construction
Location Sari, Iran
Executive stage Final Hanover
Physical Progress 100%
Commencement Date Mar., 06, 2000
Initial Duration 14 months
General works’ Quantity
Earth works 500,000 m³
concreting 13,000 m³
Reinforcement 500 tons
Form working 100,000 m²
Tonan 13,000 m²
Gabion 45,000 m

 

Brief Description & Technical Specification

BolandPayeh main service in this project is to construct a hydro-structure and related facilities for conducting the water to the right bank of Tajan River and two traditional Rivers called Spiverd and Sary. Another service of the mentioned constructed structure is to divert the river flow for river-bed improvements.