Meidouk Copper Factory

status:

is finished

contract type:

c

project domain:

industry

location:

Iran , Kerman

Meidouk Copper Factory
Contract Type Construction
Location Shahre Babak, Iran
Executive stage Final Hanover
Physical Progress 100%
Commencement Date Aug., 28, 2000
Initial Duration 15 months
General works’ Quantity
Earth works 60,000 m³
concreting 105,000 m³
Reinforcement 5,000 tons
Form working 65,000 m²
Metal works 3,500 ton

 

Brief Description & Technical Specification

The main structural, mechanical and electrical works of the Copper Concentrate Factory, was issued to BolandPayeh at Meidouk Copper Complex by the National Iranian Copper Industries Company as the client. BolandPayeh scope of work is construction of the administration buildings, concentrate production building, central crusher workshop and concrete tunnel and installation of relevant electrical and mechanical systems.