Contract Type | Construction |
Location | Bojnourd, Iran |
Executive stage | Final Hanover |
Physical Progress | 100% |
Commencement Date | May, 22, 2005 |
Initial Duration | 21 months |
General works’ Quantity | |
Earth works | 150,000 m³ |
concreting | 46,000 m³ |
Reinforcement | 5,500 tons |
Form working | 55,000 m² |
Sliding formwork | 26,000 m² |
Metal works | 850 tons |
Pile works | 2,200 m³ |
Brief Description & Technical Specification
BolandPayeh service in this project is to construct a cement factory with the capacity of 3,300 tons per day which consists of the gypsum stone crusher, clinker conveyor, clinker silos, cement feeding bonkers, cement crusher, cement transfer system, cement silos, packing and loading place, substation, facility tunnel, compressor room and returning water storages.