Contract Type | Construction |
Location | Shahroud, Iran |
Executive stage | Final Hanover |
Physical Progress | 100% |
Commencement Date | Aug., 2007 |
Initial Duration | 20 months |
General works’ Quantity | |
Earth works | 150,000 m³ |
concreting | 46,000 m³ |
Reinforcement | 5,500 tons |
Form working | 80,000 m² |
Sliding formwork | 26,000 m² |
Metal works | 850 tons |
Brief Description & Technical Specification
Bolandpayeh Company's services under this contract include construction operations for the second part of the Biarjomand Cement Factory production line, including return clinker silos, clinker silos, clinker conveying system, cement mill, cement conveying system, and cement silos with a production capacity of 3,300 tons per day.